M&S Longwell
Project

Marks & Spencer

ISG fitted out the developer’s shell at the Longwell Green site, to M&S’s design guide 10.
  • Customer
    Marks & Spencer
  • Completion Date
    01/04/2009
  • Quantity Surveyor
    Gardiner & Theobald
  • Value
    £5.2 million
  • Project Manager
    Davis Langdon LLP
  • Structural Engineer
    Melliss LLP
  • Program Duration
    22 weeks
  • Architect
    Styles & Wood
  • ME Engineer
    SDS
MS

Overview

ISG was handed the developer’s shell at the Longwell Green site on the outskirts of Bristol, to fit out to M&S’s design guide 10. This new store was one of the first to be fitted out to this design concept and would be a benchmark for future stores, which meant the client put a great emphasis on quality. Within the shell, ISG was tasked with installing a mezzanine level to increase the available floor space. The two floors were then linked by two lifts and a double escalator installation.

MS Longwell

Marks & Spencer

The fit out included an extensive clothing department, a food hall and a large home section. There was also service installation for the whole shop and the specialist equipment required for the M&S café. 

The client was impressed with the end product and the design concept has since been emulated across the country.