BBVA1
Project

BBVA

  • Customer
    BBVA
  • Procurement Route
    Single stage
  • Completion Date
    November 2012
  • Quantity Surveyor
    Gleeds
  • Value
    Confidential
  • Form Of Contract
    JCT 11 Design & Build Contract
  • Project Manager
    Gleeds
  • Area
    30,000 sq ft
  • Program Duration
    18 weeks
  • Architect
    TTSP
  • ME Engineer
    Meit Associates Ltd
BBVA_Band image

Introduction

Global group BBVA selected ISG to deliver the design and build fit out of its new headquarters in Canary Wharf.

BBVA_Band image2

The Project

ISG and architects, TTSP worked closely with the customer’s real estate team to produce a design that addressed all of BBVA’s aspirations and captured the spectacular views from the 44th floor of One Canada Square.

Working from shell and core in an occupied office tower required strict logistical management to ensure that other occupants were not inconvenienced during the 18-week programme.