ISG delivers fit out for Healthpoint, Abu Dhabi
Project

Healthpoint Clinic

Delivering over 70,000 sq ft of fit out in a live hospital environment
  • Customer
    Parsons
  • Project Manager
    Aidan Berry
  • Area
    70,000 sq ft
ISG delivers fit out for Healthpoint, Abu Dhabi

Introduction

Broken down into four phases, ISG successfully delivered over 70,000 sq ft of fit out in a live hospital environment including:

  • Dental Ward
  • Medical Screening Clinic
  • Aesthetics Clinic
  • New Pharmacy
  • New Laboratory
  • Kitchen Extension
ISG delivers fit out for Healthpoint, Abu Dhabi
All of the work was carried out in a live environment and this is an area where ISG’s processes and planned approach to work and minimising
disruption really was important to the successful outcome of the project. We are continuing to deliver new projects within the hospital and this is testament to hard work and effort made by all both from ISG but also the consultant and clients teams.
ISG delivers fit out for Healthpoint, Abu Dhabi

Challenges

The most challenging part of this project was completing the works in a fully operating hospital environment without causing any disruptions to its daily running. To secure the successful outcome of the project, ISG’s specialist teams implemented processes and a planned approach to working in order to minimise disruption to the client.

Healthpoint Middle East  - ISG

ISG was appointed to undertake four phases of works. The first was to replace three AHUs and associated return air units. The second saw the team install an additional 24 AHUs across the VIP hospital. The third stage included the modifications and upgrades of existing areas to both MEP services and décor. The next stage saw us work on the; dental ward; medical screening clinic; aesthetics clinic; new pharmacy; new laboratory; and a kitchen extension. 

ISG delivers fit out for Healthpoint, Abu Dhabi
Following the successful completion of the first four phases, ISG was tasked with delivering the hospital’s L3 plastics ward - including all medical gas installations, Nurse Call systems and MEP infrastructure resilience with UPS back up for critical equipment. The space was completed in early 2018.