- Customer
- Coca-Cola Enterprises Limited
-
- Procurement Route
- Single Stage Design & Build
-
- Completion Date
- 03/02/2012
-
- Quantity Surveyor
- Faithful & Gould
-
- Value
- £844,000
-
- Form Of Contract
- JCT 2005 Design & Build
-
- Project Manager
- Faithful & Gould
-
- Structural Engineer
- Waterman Structures Limited
-
- Area
- 16,145 sq ft
-
- Program Duration
- 33 weeks
-
- Architect
- Bond Bryan
-
- ME Engineer
- Silcock Leedham
.jpg?h=328&w=512&hash=26660C0D12AEBBA14951FB11533F7234&usecustomfunctions=1¢ercrop=1 )
Introduction
ISG secured this design and build project with Coca-Cola Enterprises Limited, to enhance production facilities at its Sidcup manufacturing and distribution site. The fast-track scheme saw ISG extend an existing warehouse building to accommodate two new beverage production lines.
The Project
The single-storey steel frame structure occupies an infill site between existing production facilities, at the world’s third largest independent Coca-Cola bottler. ISG also created a new recycling shelter as part of the project and carried out a range of hard landscaping finishes. Working across a busy, live site, we developed a robust schedule of works to ensure there was no disruption to production during the project.