ISG UAE fit out for ICD Brookfield Place
Project

Community Hub,  ICD Brookfield Place

The project involved the complete fit-out of a retail space located at the ground floor of ICD Brookfield Place, one of the prime retail spaces in Dubai
  • Completion Date
    25 April 2021
  • Quantity Surveyor
    Turner and Townsend
  • Area
    1,500 sq ft
  • Program Duration
    10 weeks
  • Architect
    Roar Design (ID)
ISG UAE fit out for ICD Brookfield Place

The project

The project involved the complete fit-out of a retail space located at the ground floor of ICD Brookfield

Place, one of the prime retail spaces in Dubai now, which went live towards the end of 2020. This space was fitted out in line with the ID design provided by Roar Design with the MEP design developed by ISG inhouse.

The space is intended to cater to needs of the client which includes marketing, art exhibitions, tutorials, presentations etc. The scope included all MEP installations, AV, IT, security installations, gypsum walls, fabric ceilings, textured wall finishes, wallpaper, customisable furniture, fixed furniture, wooden/metal ceilings, vinyl flooring, carpets, wall panelling, façade works.

The fit-out was completed from the ground up with the blockwork demise walls also built by ISG under a different work order, as part of the framework.

ISG UAE fit out for ICD Brookfield Place

Challenges

  1. MEP design was in-house through our supply chain and TSM team and the ID design was through Roar design. Co-ordination was a challenge with the tight timeline.
  2. Challenging timeline considering demise walls, design and execution to be carried out in 2 and a half months.
  3. Small area with limited space for high level access. Slab to slab height of 8m.
ISG UAE fit out for ICD Brookfield Place

What we did

  1. Having weekly workshops with ID designer to develop the design to shop drawings and taking the MEP design in parallel with consistent communication on the challenges to the ID designer so that both designs would sync well from the get-go.
  2. Fast tracking MEP design and executing high level works early on fixed scaffolding built for the construction of block demise walls.
  3. Working both shifts by staggering trades for better site coordination.