- Customer
- Abu Dhabi Capital Group
-
- Procurement Route
- Traditional
-
- Completion Date
- July 2017
-
- Quantity Surveyor
- BWA
-
- Value
- AED 5m
-
- Form Of Contract
- FIDIC
-
- Project Manager
- BWA
-
- Area
- 4,000 sq ft
-
- Program Duration
- 10 weeks
-
- Architect
- TGP Design
-
- ME Engineer
- TUV Sud
Introduction
In just 10 weeks, ISG completed the quirky Moombai & Co. Café and Bar, located at The H Dubai hotel on One Sheikh Zayed Road.
The project
With just 25 traditional Parsi cafés left in India, Moombai & Co. promises much-loved cuisine and an authentic atmosphere.
ISG delivered the fit out of the unique dining space with exposed brick, mahogany furniture, Italian marble table tops, bent cane chairs and pendulum wall clocks.
Once the team were on site, additional scope was uncovered. We managed to complete all additional work in the same intended time frame.
The original design by TGP Design was value engineered by ISG until the value matched the client budget. The ISG design team worked closely with BWA and TGP Design to source the alternative materials that were within budget and met the specification requirements.
The team also demolished the existing kitchen, while the restaurant was still operational. This was carefully planned with the H Hotel’s operations team and involved phasing the demolition process and working out of hours.
We built a new entrance façade which required us to work in a busy hotel live environment.